Ngaka Coal Project | Atomic Resources | Southern Tanzania, Australia | Study work | Feasibility study and mining infrastructure design | Undisclosed | 2010 |
Braakfontein Coal Project | Keaton Energy | KwaZulu Natal, South Africa | Conceptual study | Mine design and mine planning for a combined opencast and underground mine | ZAR 500,000 | 2012 |
Eloff Coal Mine Project | Total Coal SA | South Africa | Greenfields development of 7 million tons per annum open-cut and underground mine with the coal processing plant and supporting infrastructure for the production of both export and Eskom products | Scope of work involves conducting a conceptual study which covers the mining operations, the coal processing facilities, product dispatch options and all surface support infrastructure and supply of bulk services. | Capital expenditure managed by the consultant amounts to ZAR 2.2 billion | 2008-2010 |
Marapule South Coal Project | Hodges | Botswana | Conceptual study | Undertake a complete conceptual study | ZAR | 2012 |
Sterkfontein Coal Project | Keaton Energy | Mpumalanga, South Africa | Conceptual study | Mine design and mine planning for an underground mine | ZAR 500,000 | 2012 |
Dukwe Project | African Copper | Botswana | Infrastructure and opencast mining project | EPCM | ZAR766 million | 2005-2006 |
No 10 Shaft Head Frame Design | Resolution Copper Mining | North America | No 10 Shaft head frame design | No 10 Shaft head frame design | US$445,890 | 2006 |
Number 10 Shaft Head Frame Construction | Resolution Copper Mining | North America | Number 10 Shaft dead frame construction – approval of construction queries, methods and drawing details | Number 10 Shaft dead frame construction – approval of construction queries, methods and drawing details | US$157,380 | 2008-2009 |
Argyle Diamonds UG Expansion Project | Rio Tinto Diamonds | Australia, West Kimberley region | Argyle has completed a feasibility study for the development of an underground block cave mining operation | Includes power station upgrades, surface secondary crusher circuit, u/g MHS and conveying system, two u/g crushing stations, two u/g dewatering pump stations, all surface and u/g services, power station works and overhead line and portal sub station | US$1.658 billion budget managed by consultant | In progress |
Magazynskraal / Sedibelo East Project | Boynton Investments | Rustenburg, South Africa | Surface infrastructure and underground engineering design for the Magazynskraal/Sedibelo Project | Surface infrastructure and underground engineering design for the Magazynskraal/Sedibelo Project | ZAR7.9 million | 2011 – 2012 |
Admiral Bay Project | Kagara | Australia West, Broom | Pre-feasibility | To establish all surface and u/g services and infrastructure requirements necessary for the exploitation of the Admiral Bay ore body – includes the facilities to treat the ore | A$565,850 (total project value still to be determined) | In progress |