Platinum

RSV has a long history of performing projects in the Platinum mining and minerals sector. Our projects cover the full spectrum of concept studies, through pre-feasibility studies to feasibility studies and culminating in the engineering (detailed design and drawings) procurement and construction management (EPCM) component of access to the ore body, infrastructure and process plants. We have compiled competent and qualified persons’ reports and completed economic assessments. We have also completed due diligence studies for some of our clients.

 Access to the orebody covers all the aspects for surface and underground mining, such as open cast operation design, declines, vertical shafts, and sub-shaft systems.

 We have completed work for all the major, and many junior mining houses. Anglo-American Platinum, Impala Platinum, Lonmin (now Sibanye Stillwater), Royal Bafokeng Platinum, Glencore, Ivanhoe, etc.

Rein Koelmans

RSV
Tel: +27 10 109 9190
e-mail: rsv@rsv.co.za

Related Projects

Project NameClient NameProject LocationProject DescriptionScope of ServicesProject Value
2.4 MTPA TRP Marenskry Mining ProjectTwo Rivers PlatinumSouth AfricaEPCM servicesEPCMUndisclosed
K4 Shaft EPCMSibanye StillwaterSouth AfricaEPCM servicesEPCMUndisclosed
Amandelbult Middellagte PFSAnglo American PlatinumSouth AfricaStudy workPre-feasibility studyUndisclosed
K4 MerenskyLominSouth AfricaMining Engineering servicesMining Engineering servicesUndisclosed
Main and Ventilation Shaft Feasibility Study to EPCM No 16 ShaftImpala PlatinumRustenburg, South AfricaMain and ventilation shaft feasibility study to EPCMMain and ventilation shaft feasibility study to EPCMZAR4.5 billion
K3 Sub Decline ShaftLonminRustenburg, South AfricaEPCM servicesEPCMZAR1.5 billion
BRPM Phase 3 ImplementationRoyal Bafokeng HoldingsRustenburg, South AfricaProject implementationProject implementationZAR94 million
Siphumelele No 1 Shaft UG2Anglo American PlatinumRustenburg, South AfricaExploitation concept studyProvide a comprehensive project management service. Includes management of nominated sub-consultants from initiation of the project to handover of the study documentsZAR5.3 million
K4 Ore Reserve Development ProjectLonminRustenburg, South AfricaEPCM servicesEPCMZAR3.3 billion
Turffontein MerenskyAnglo American PlatinumRustenburg, South AfricaDecline extension 34 Level and feasibility study – CIVPrepare pre-feasibility upfrontZAR2.1 million
Re-statement for Khuseleka Ore Reserve Development Project (KORP)Anglo American PlatinumRustenburg, South AfricaRe-statement for Khuseleka Ore Reserve Development Project (KORP)Re-statement of the work to complete the remaining project scopeZAR2.3 million
Khuseleka Mine (Townlands) Ore Replacement ProjectAnglo American PlatinumRustenburg, South AfricaKhuseleka Mine (Townlands) Ore Replacement Project - designKhuseleka Mine (Townlands) Ore Replacement Project - designZAR22 million
Khomanani UG2 26 LevelAnglo American PlatinumRustenburg, South AfricaConcept studyConcept study to detail and establish whether or not there is a business case that could meet the investment criteria hurdle ratesZAR4.6 million
Rowland MiddelkraalLonminRustenburg, South AfricaFeasibility study Phase 1 and pre-feasibility study (Phase 2 & 3): engineering designFeasibility study Phase 1 and pre-feasibility study (Phase 2 & 3): engineering designZAR6.2 million
Pandora JV Plan 4 ProjectLonminRustenburg, South AfricaEPCMEPCMZAR20 million
Magazynskraal / Sedibelo East ProjectBoynton InvestmentsRustenburg, South AfricaSurface infrastructure and underground engineering design for the Magazynskraal/Sedibelo ProjectSurface infrastructure and underground engineering design for the Magazynskraal/Sedibelo ProjectZAR7.9 million
Waterval Bathopele Phase 5 FeasibilityAnglo American PlatinumRustenburg, South AfricaEPCM servicesEPCM servicesUndisclosed
Styldrift No 2 Shaft Merensky and UG2Royal Bafokeng HoldingsRustenburg, South AfricaConcept studyConduct a review and assistance with the concept study for the exploitation of Styldrift No 2 Merensky and UG2 resourcesZAR4.5 million
Rowland Merensky Sub-decline ShaftLonminRustenburg, South AfricaEPCM servicesEPCMUndisclosed
Pandora E3 60kton Feasibility revisionLonminRustenburg, South AfricaPandora E3 60kton feasibility revisionAmend existing study report to establish the strategic fit and attractiveness of the business case for the business unitUndisclosed
Magazynskraal ProjectBoynton InvestmentsSouth AfricaDesign and study workSurface infrastructure and underground engineering design for pre- and feasibility study for Magazynskraal/Sedibelo East PlatinumUndisclosed
Khuseleka 1 Merensky 28 – 30 Level Concept StudyAnglo American PlatinumRustenburg, South AfricaConcept studyConcept studyZAR5.5 million
Khomanani 37-41L Merensky Concept StudyAnglo American PlatinumRustenburg, South AfricaConcept studyConcept studyZAR2.6 million
Hossy Shaft Execution ProjectLonminRustenburg, South AfricaEPCM servicesEPCMUndisclosed
BRPM Phase 3 Feasibility StudyRoyal Bafokeng HoldingsRustenburg, South AfricaFeasibility studyFeasibility studyZAR340,000 million
Bathopele Phase 5 Feasibility StudyAnglo American PlatinumRustenburg, South AfricaFeasibility studyFeasibility studyZAR43.2 million
Impala Flash Dryer PlantImpala PlatinumRustenburg, South AfricaFeasibility study, EPCM servicesFeasibility study and EPCM contract for the implementation phase of the Flash Dryer Project, including engineering (all disciplines), procurement, construction management, safety management, commissioning and overall project managementUndisclosed
Brakfontein Merensky ProjectAnglo American PlatinumSouth AfricaEngineering, design and procurementEngineering, design and procurementZAR1.1 billion
Brakfontein ImplementationAnglo American PlatinumSouth AfricaEPCM servicesEPCMUndisclosed
9 Shaft Lower UG2 DeclineImpala PlatinumSouth AfricaControl budget estimateControl budget estimateUndisclosed
12 Shaft UG2Impala PlatinumSouth AfricaFeasibility studyFeasibility studyZAR10.7 million
Spitzkop ProjectEastern PlatinumSouth AfricaFeasibility study to EPCMFeasibility study to EPCMUndisclosed
Sedibelo Feasibility Study ReviewBarrickSouth AfricaStudy workStudy reviewUndisclosed
Pandora 240ktpm ProjectPandora Joint VentureSouth AfricaFeasibility studyFeasibility studyUndisclosed
Limpopo Phase 2 ProjectLonminSouth AfricaStudy workStudy phase (scope determination of Limpopo Phase 2 feasibility and Baobab optimisation)Undisclosed
K4 ShaftLonminRustenburg, South AfricaMain and ventilation shaftEPCMZAR3.2 billion
Amandelbult Mine ProjectAnglo American PlatinumSouth AfricaMain and ventilation shaftEPCMUndisclosed
Akanani ProjectLonminSouth AfricaStudy workStudy phase (scoping, pre-feasibility, feasibility and detailed design)Undisclosed
Akanani Infrastructure ProjectLonminSouth AfricaStudy workPre-feasibility studyUndisclosed
12 Shaft Lower UG 2 DeclineImpala PlatinumSouth AfricaControl budget estimateControl budget estimateUndisclosed
Zandfontein Decline ProjectEastern PlatinumSouth AfricaDesign reviewDesign review and development of EPCM contract and a control budget estimateUndisclosed
Kennedy’s Vale & SpitzkopEastern PlatinumSouth AfricaProgramme managementProgramme management of both Kennedy’s Vale & Spitzkop ProjectsUndisclosed
Kareespruit ProjectEastern PlatinumSouth AfricaStudy workContinue with feasibility study and develop a control budget estimateZAR13 million
Waterval ProjectAnglo American PlatinumSouth AfricaEPCMEPCMZAR150 million
Turffontein Decline ProjectAnglo American PlatinumSouth AfricaUnderground expansionFeasibility to EPCMZAR350 million
Middelpunt Hill Underground 2 ProjectAnglo American PlatinumSouth AfricaUnderground developmentEPCMZAR1.3 billion
Kroondal Mine ProjectAquarius PlatinumSouth AfricaK6 partial pre-feasibility studyK6 partial pre-feasibility studyUndisclosed
Boschfontein ShaftAnglo American PlatinumSouth AfricaStudy workConceptual and pre-feasibility studyUndisclosed
Frank Underground 2 ProjectAnglo American PlatinumSouth AfricaUnderground expansionConcept phase to EPCMZAR1.98 billion