Platinum
RSV has a long history of performing projects in the Platinum mining and minerals sector. Our projects cover the full spectrum of concept studies, through pre-feasibility studies to feasibility studies and culminating in the engineering (detailed design and drawings) procurement and construction management (EPCM) component of access to the ore body, infrastructure and process plants. We have compiled competent and qualified persons’ reports and completed economic assessments. We have also completed due diligence studies for some of our clients.
Access to the orebody covers all the aspects for surface and underground mining, such as open-cast operation design, declines, vertical shafts, and sub-shaft systems.
We have completed work for all the major, and many junior mining houses. Anglo-American Platinum, Impala Platinum, Lonmin (now Sibanye Stillwater), Royal Bafokeng Platinum, Glencore, Ivanhoe, etc.
![](https://rsv.co.za/wp-content/uploads/2022/08/7fa4bfc26a9bc74370cc4e149be793a4-Koelmans_R.jpg)
Rein Koelmans
RSV
Tel: +27 10 109 9190
e-mail: rsv@rsv.co.za
Related Projects
Project Name | Client Name | Project Location | Project Description | Scope of Services | Project Value |
---|---|---|---|---|---|
2.4 MTPA TRP Merensky Mining Project | Two Rivers Platinum | South Africa | Full EPCM Services for Five Decline Shaft Cluster and Surface and Underground Infrastructure | EPCM | Undisclosed |
K4 Shaft | Sibanye Stillwater | South Africa | Full EPCM Services for Vertical Main and Ventilation Shafts and Surface and Underground Infrastructure | EPCM | Undisclosed |
Amandelbult Middellagte PFS | Anglo American Platinum | South Africa | Engineering and Design Services for Pre-feasibility Study | Pre-feasibility Study | Undisclosed |
K4 Merensky | Lomin | South Africa | Mining Engineering Services | Mining Engineering Services | Undisclosed |
No 16 Shaft Project | Impala Platinum | Rustenburg, South Africa | Project Management, Engineering and Design Services for Vertical Main and Ventilation Shafts and Surface and Underground Infrastructure | Feasibility Study and full EPCM Services | ZAR4.5 billion |
K3 Sub-decline Shaft | Lonmin | Rustenburg, South Africa | Full EPCM Services for Sub-decline Shaft System | EPCM | ZAR1.5 billion |
BRPM Phase 3 Implementation Project | Royal Bafokeng Holdings | Rustenburg, South Africa | Full EPCM Services | EPCM | ZAR94 million |
Siphumelele No 1 Shaft UG2 | Anglo American Platinum | Rustenburg, South Africa | Project Management, Engineering and Design Services forMine Concept Study | Concept Study | ZAR5.3 million |
K4 Ore Reserve Development Project | Lonmin | Rustenburg, South Africa | Full EPCM Services | EPCM | ZAR3.3 billion |
Turffontein Merensky | Anglo American Platinum | Rustenburg, South Africa | Engineering and Design Services for Pre-feasibility Study and Up-front Engineering for Decline Shafts Extension down to 34 Level | PFS and Up-front Engineering Services | ZAR2.1 million |
Khuseleka (Townlands) Shaft Ore Reserve Development Project (KORP) | Anglo American Platinum | Rustenburg, South Africa | Engineering and Design Services for Scoping Study and Re-statement of the Work to Complete the Remaining Project Scope | Scoping Study | ZAR2.3 million |
Khuseleka (Townlands) Shaft Ore Replacement Project (KORP) | Anglo American Platinum | Rustenburg, South Africa | Engineering and Detail Design Services | Engineering and Design Services | ZAR22 million |
Khomanani UG2 Mine Expansion to 26 Level | Anglo American Platinum | Rustenburg, South Africa | Concept Study to determine the Investment Business Case | Concept Study | ZAR4.6 million |
Rowland Middelkraal Shaft Project | Lonmin | Rustenburg, South Africa | Engineering and Design Services for the Feasibility Study (Phase 1) and Pre-feasibility Study (Phases 2 & 3) | PFS and FS | ZAR6.2 million |
Pandora JV Plan 4 Project | Lonmin | Rustenburg, South Africa | Engineering and Design Services for Feasibility Study for New Shaft Project | Feasibility Study | ZAR20 million |
Magazynskraal-Sedibelo East Project | Boynton Investments | Rustenburg, South Africa | Engineering and Detail Design Services for Surface and Underground Infrastructure | Engineering and Design Services | ZAR7.9 million |
Waterval Bathopele Phase 5 Feasibility Study | Anglo American Platinum | Rustenburg, South Africa | Engineering and Design Services for Feasibility Study | Feasibility Study | Undisclosed |
Styldrift No 2 Shaft Merensky and UG2 | Royal Bafokeng Holdings | Rustenburg, South Africa | Engineering and Design Services for Concept Study | Concept Study | ZAR4.5 million |
Rowland Merensky Sub-decline Shaft | Lonmin | Rustenburg, South Africa | Full EPCM Services | EPCM | Undisclosed |
Pandora E3 60ktpm Feasibility Study Upgrade | Lonmin | Rustenburg, South Africa | Engineering and Design Services for Feasibility Study Update to confirm Business Case | Feasibility Study | Undisclosed |
Magazynskraal-Sedibelo East Project | Boynton Investments | South Africa | Engineering and Design Services for Pre-feasibility Study and Feasibility Study for Surface and Underground Infrastructure | PFS and FS | Undisclosed |
Khuseleka 1 Merensky Shaf t from 28 to 30 Level Extension | Anglo American Platinum | Rustenburg, South Africa | Engineering and Design Services for Feasibility Study | Feasibility Study | ZAR5.5 million |
Khomanani Merensky Shaft from 37 to 41 Level Extension | Anglo American Platinum | Rustenburg, South Africa | Engineering and Design Services for Concept study | Concept study | ZAR2.6 million |
Hossy Shaft Implementation Project | Lonmin | Rustenburg, South Africa | Full EPCM Services | EPCM | Undisclosed |
BRPM Phase 3 Feasibility Study | Royal Bafokeng Holdings | Rustenburg, South Africa | Engineering and Design Services for Feasibility Study | Feasibility Study | ZAR3.4 million |
Bathopele Phase 5 Feasibility Study | Anglo American Platinum | Rustenburg, South Africa | Engineering and Design Services for Feasibility Study | Feasibility Study | ZAR43.2 million |
Flash Dryer Project | Impala Platinum | Rustenburg, South Africa | Engineering and Detail Design Services for Project Feasibility Study, and Project Implementation Full EPCM Services | Feasibility Study and EPCM | Undisclosed |
Brakfontein Merensky Project | Anglo American Platinum | South Africa | Engineering, Design and Procurement Services | Engineering and Procurement | Undisclosed |
Brakfontein Implementation Project | Anglo American Platinum | South Africa | Full EPCM Services | EPCM | Undisclosed |
9 Shaft Lower UG2 Decline Project | Impala Platinum | South Africa | Engineering and Design Services for Feasibility Study and Control Budget Estimate | Feasibility Study | Undisclosed |
12 Shaft UG2 Project | Impala Platinum | South Africa | Engineering and Detail Design Services for Feasibility Study and Full EPCM Services | FS and EPCM | ZAR10.7 million |
Spitzkop Project | Eastern Platinum | South Africa | Engineering and Design Services for Feasibility Study and Full EPCM Services | FS and EPCM | Undisclosed |
Sedibelo Project Feasibility Study Review | Barrick | South Africa | Engineering and Design Services for Review of Feasibility Study | Feasibility Study | Undisclosed |
Pandora 240ktpm Project | Pandora Joint Venture | South Africa | Engineering and Design Services for Feasibility Study | Feasibility Study | Undisclosed |
Limpopo Phase 2 Project | Lonmin | South Africa | Engineering and Design Services for Scoping Study for Limpopo Phase 2 and Baobab Optimisation Projects | Scoping Study | Undisclosed |
K4 Shaft Project | Lonmin | Rustenburg, South Africa | Full EPCM Services for New Vertical Main and Ventilation Shafts | EPCM | ZAR3.2 billion |
Amandelbult Mine No 2 Shaft Project | JCI Rustenburg Platinum Mines | South Africa | Full EPCM Services for New Vertical Shaft Project | EPCM | Undisclosed |
Akanani Project | Lonmin | South Africa | Engineering and Design Services for Scoping, Pre-feasibility and Feasibility Studies and Detail Design Phase | Engineering and Design Services | Undisclosed |
Akanani Infrastructure Project | Lonmin | South Africa | Engineering and Design Services for Pre-feasibility Study | PFS | Undisclosed |
No 12 Shaft Lower UG 2 Project | Impala Platinum | South Africa | Engineering and Design Services for Feasibility Study and Control Budget Estimate | Feasibility Study | Undisclosed |
Zandfontein Decline Project | Eastern Platinum | South Africa | Engineering and Design Services for Design Review and preparation of Control Budget Estimate | Design Review and CBE | Undisclosed |
Kennedy's Vale & Spitzkop Projects | Eastern Platinum | South Africa | Full EPCM Programme Management Services | EPCM | Undisclosed |
Kareespruit Project | Eastern Platinum | South Africa | Engineering and Design Services for Feasibility Study and Control Budget Estimate | Feasibility Study | ZAR13 million |
Waterval Project | Anglo American Platinum | South Africa | Full EPCM Services | EPCM | ZAR150 million |
Turffontein Decline Shaft Project | Anglo American Platinum | South Africa | Engineering and Design Services for Underground Expansion Project Feasibility Study and EPCM | FS and EPCM | ZAR350 million |
Middelpunt Hill Underground Project | Anglo American Platinum | South Africa | Full EPCM Services for Underground Development Project | EPCM | ZAR1.3 billion |
Kroondal Mine Project | Aquarius Platinum | South Africa | Engineering and Design Services for K6 Pre-feasibility Study | Pre-feasibility Study | Undisclosed |
Boschfontein Shaft | Anglo American Platinum | South Africa | Engineering and Design Services for Concept and Pre-feasibility Studies | Concept and PFS | Undisclosed |
Frank 2 Shaft Underground Expansion Project | Anglo American Platinum | South Africa | Engineering and Design Services for Concept Study, Pre-Feasibility Study, Feasibility Study and Full EPCM Services | Studies and EPCM | ZAR1.98 billion |