RSV (SA) is a stand-alone empowerment company dedicated to on-mine stay-in-business projects and infrastructure in the government and parastatal sectors, focusing on four market areas:

–  Mining Projects Surface and Underground
–  Mine Employee Welfare Infrastructure
–  Local Government Publich Works
–  Private Public Sector Industrial Projects

RSV (SA) has the capacity to take on projects of any size with the support of the RSV Group of Linked Enterprises where additional technological or managerial skills may be required.

During 2013, RSV (SA) expanded its services to include plants and processing. 

Click here to find out more about RSV (SA) Process Division.

Rein Koelmans CEO: RSV (SA) (Pty) Ltd

MBL; B.Sc Engineering (Mining); Project Management Professional (PMP); Member of the Engineering Council of South Africa; Member of the Project Management Institute of South Africa; Associate Member of the Association of Mine Managers of South Africa; Fellow of the Southern African Institute of Mining and Metallurgy.

Tel: +27 10 109 9209
e-mail: rsv@rsv.co.za

Related Projects

Project NameClient NameProject LocationProject DescriptionScope of ServicesProject ValueDuration
Turffontein MerenskyAnglo American PlatinumRustenburg, South AfricaDecline extension 34 Level and feasibility study – CIVPrepare pre-feasibility upfrontZAR2.1 million2011 – Current
Styldrift No 2 Shaft Merensky and UG2Royal Bafokeng HoldingsRustenburg, South AfricaConcept studyConduct a review and assistance with the concept study for the exploitation of Styldrift No 2 Merensky and UG2 resourcesZAR4.5 million2011
Siphumelele No 1 Shaft UG2Anglo American PlatinumRustenburg, South AfricaExploitation concept studyProvide a comprehensive project management service. Includes management of nominated sub-consultants from initiation of the project to handover of the study documentsZAR5.3 million2011 – Current
Rowland MiddelkraalLonminRustenburg, South AfricaFeasibility study Phase 1 and pre-feasibility study (Phase 2 & 3): engineering designFeasibility study Phase 1 and pre-feasibility study (Phase 2 & 3): engineering designZAR6.2 million2011 - 2012
Rowland Merensky Sub-decline ShaftLonminRustenburg, South AfricaEPCM servicesEPCMUndisclosed2011
Re-statement for Khuseleka Ore Reserve Development Project (KORP)Anglo American PlatinumRustenburg, South AfricaRe-statement for Khuseleka Ore Reserve Development Project (KORP)Re-statement of the work to complete the remaining project scopeZAR2.3 million2011 – Current
Palabora Lift II ProjectPalabora Mining CompanyPhalaborwa, South AfricaLift II Order of Magnitude StudyLift II order of magnitude studyZAR3.7 million2011
Lift II ProjectPalabora Mining CompanyPhalaborwa, South AfricaOrder of magnitude study and early works engineeringOrder of magnitude study and early works engineeringZAR3.6 million2011
Lift II ProjectPalabora Mining CompanyPhalaborwa, South AfricaPre-feasibility studyPre-feasibility studyZAR43.6 Million2012 - Current
Khuseleka 1 Merensky 28 – 30 Level Concept StudyAnglo American PlatinumRustenburg, South AfricaConcept studyConcept studyZAR5.5 million2011
Khomanani UG2 26 LevelAnglo American PlatinumRustenburg, South AfricaConcept studyConcept study to detail and establish whether or not there is a business case that could meet the investment criteria hurdle ratesZAR4.6 million2011 – Current
Khomanani 37-41L Merensky Concept StudyAnglo American PlatinumRustenburg, South AfricaConcept studyConcept studyZAR2.6 million2010 – 2011
Hossy Shaft Execution ProjectLonminRustenburg, South AfricaEPCM servicesEPCMUndisclosed2008-2017